PRE-ISSUE QA CHECKLIST — ICT DRAWING PACKAGE ============================================================= Free template from ICT Design Partners — ictdesignpartners.com Run by someone OTHER than the author, against a named standard set, before any package leaves the office. ~20 minutes that catch most of what otherwise surfaces as field RFIs. ============================================================= Project: ______________ Set/Rev: ______ Reviewer: ________ Date: ____ / ____ / ______ Standards basis: BICSI TDMM, ANSI/TIA-568/-569/-606/-607, NEC + AHJ amendments, project spec SHEET MECHANICS [ ] Sheet index matches the actual sheets (count, titles, revs) [ ] Every sheet: correct title block, project no., rev, date [ ] Revision clouds + deltas match the rev narrative [ ] North arrows and scales present and correct [ ] Cross-references resolve (details, sections, "see sheet X") PATHWAYS & SPACES [ ] Tray/conduit sizing shown and within fill limits (calc referenced, not implied) [ ] Pathway separation from power per TIA-569 noted where close [ ] TR/ER layouts: working clearances, door swing, plywood, dedicated outlets, lighting noted [ ] Riser/sleeve locations match between floor plans and risers [ ] Fire-rated penetrations identified with firestop callouts CABLE PLANT [ ] Horizontal lengths within channel limits (worst-case run checked, not the average) [ ] Backbone strand/pair counts match riser diagram and BOM [ ] Fiber loss budgets calculated and on the drawings [ ] Cable types/ratings match the environment (plenum/riser/OSP) GROUNDING & ADMINISTRATION [ ] TBB/TGB/bonding shown per TIA-607, sized, and routed [ ] Labeling scheme stated on the drawings and consistent with the project's TIA-606 convention [ ] Outlet IDs on plans match the schedule (spot-check 10) COORDINATION [ ] Overlaid against current architectural backgrounds (right rev!) [ ] Checked against mechanical for tray/duct conflicts [ ] Checked against electrical for shared pathway and power needs [ ] AHJ/permit comments from prior cycles addressed and closed PACKAGE [ ] Spec sections referenced actually exist in the spec book [ ] BOM quantities spot-checked against plans (pick 5 lines) [ ] General notes current (no boilerplate from another project) [ ] Responsible-party block + seal/signature space correct Findings (cite the standard for each): _____________________________________________________________ _____________________________________________________________ Result: [ ] Cleared to issue [ ] Corrections required No warranty; adapt to your practice. The checklist is the floor, not the ceiling.